External wall insulation (EWI) places the insulation on the external face of the walls. The structure — slabs, party walls, ring beams — then ends up entirely on the warm side, protected by a continuous layer of insulation that wraps the building. Because the insulation passes in front of the junctions rather than being interrupted by them, most junction thermal bridges (slab edges, party walls, floors) are strongly reduced. EWI does not "remove" every bridge, but restores the continuity of the insulation and essentially leaves residual bridges at penetrations and connections, which are treated case by case and verified by calculation or thermography.
A junction thermal bridge arises from the interruption of the insulation by a conductive element. With internal insulation, each slab and each party wall pierces the insulating layer. With EWI, the insulation is moved to the outside: it forms an envelope that passes in front of these elements without discontinuity. Two physical consequences:
EWI acts effectively on the majority of critical junctions, but residual bridges remain, to be treated in detail:
| Critical junction | Effect of EWI | Point of vigilance |
|---|---|---|
| Slab edges, intermediate floors | Strongly reduced | Continuity of the overlap |
| Party walls | Almost removed (structure on the warm side) | — |
| Reveals and window perimeter | Reduced by the insulation return | Return up to the frame |
| Cantilevered balconies, parapets | Partly treated | Residual fin, waterproofing |
| Fixings, rails, anchors | Point bridges χ | Density and type of fixing |
The quality of an EWI depends first on the continuity of the insulating layer. Panel systems achieve it with jointed boards, whose joints and fixings can create point bridges if the installation is imperfect. A facade render applied continuously, without panels or joints, aims to limit these discontinuities: this is the logic of the system distributed by Isoltech Green in Europe. This continuity of application is an advantage at critical junctions (reveals, parapets, base of walls), but it never removes the need to treat penetrations or to verify the result by measurement.
After the works, the reduction of thermal bridges is established by standardised calculation (EN ISO 14683 / ISO 10211, integrated into the energy balance depending on local regulations) or by in-situ thermography (EN 13187), which visualises the residual cold areas. Results from the laboratory (standardised tests), from simulation (numerical model) and from the building site (real measurement) must be distinguished, as they do not carry the same weight. A calculated gain is only confirmed after checking the workmanship.
This guide complements the Thermal correction of buildings dossier and the Thermal bridges cluster. The comparison with internal insulation is detailed in the IWI & residual bridges guide. Isoltech Green is a European distributor; the choice of a solution falls to a project study.