Internal wall insulation (IWI) places the insulation on the internal face of the walls. The structure — slabs, party walls, floors — then stays on the cold side, and every element that meets the facade crosses the insulating layer. The result is residual thermal bridges at intermediate floors, party walls and junctions, which IWI cannot wrap the way external insulation would. These bridges are limited by insulation returns, but they remain. In return, IWI is more economical, does not affect the facade and suits heritage or protected buildings.
Because the insulation is on the inside, it is interrupted wherever a structural element butts against the facade wall:
They are not removed, but they are reduced by workmanship measures:
The extent of the residual bridge is determined by the default values of EN ISO 14683 or by a detailed ISO 10211 calculation. The risk of condensation, on the surface as within the wall, is assessed by EN ISO 13788 (the fRsi factor and the Glaser method).
With IWI, the load-bearing wall ends up on the cold side of the insulation. The water vapour from inside can then condense in contact with the cold wall if humidity management is insufficient. This risk, specific to IWI, is controlled by a suitable vapour barrier or vapour control layer on the inside and by effective ventilation of the dwelling. This is an important difference from EWI, which leaves the wall on the warm, dry side.
Despite its residual bridges, IWI remains the right choice in several situations:
| Situation | Why IWI |
|---|---|
| Heritage facade or protected area | The external appearance must be preserved; EWI is prohibited or not advised |
| Shared boundaries, alignment with the street | No room available on the outside |
| Constrained budget, room-by-room renovation | Lower cost, works that can be staged |
| Intermittently heated premises | Faster response in reaching temperature |
As with any intervention, the reduction achieved is established by standardised calculation (EN ISO 14683 / ISO 10211, integrated into the energy balance depending on local regulations) or by in-situ thermography (EN 13187), targeting the party-wall corners and the floor ends. Results from the laboratory, from simulation and from the building site are distinguished, as they carry different weight.
This guide complements the Thermal correction of buildings dossier and the Thermal bridges cluster. The external strategy is detailed in the Treatment by EWI guide. Isoltech Green is a European distributor; the choice of a solution falls to a project study.